Nature of the work: Upgrade the F5 chassis systems
Data Center(s): Lindquist Center (LC) and Information Technology Facility (ITF)
The F5 chassis systems host all F5 GTM/DNS and LTM systems in the following way:
ITF chassis 1 (ITF primary LTM, ITF GTM/DNS)
ITF chassis 2 (ITF secondary LTM)
LC chassis 1 (LC primary LTM, LC GTM/DNS)
Each chassis will be upgraded, one at time, resulting in the GTM/DNS and LTM systems hosted on the chassis being unavailable for a period of time.
The LTM systems are redundant and services will be moved between the primary and secondary systems as needed. The GTM/DNS systems are redundant and provide the same data. No more than one GTM/DNS and one LTM system will be unavailable at any time.
Expected impact on services: None
Expected duration: 2 hours in LC; 2 hours in ITF
Time: 4:00 AM to 8:00 AM
Nature of the work: Upgrade NetApp clusters
Data Center(s): Lindquist Center (LC) and Information Technology Facility (ITF)
Expected impact on services: Each volume will experience two brief (10-30 seconds) pauses in IO
Time: 6:00 AM to 9:00 AM
For additional information about this work, please see the Data Center Infrastructure Work for Saturday, November 19, 2016.