Dates affected
-

Nature of the work: As part of the Data Center Network Segmentation Project, the Enterprise Infrastructure (EI) storage subnet in the Lindquist Center 14 (LC14) datacenter will be migrated to a new network VRF.

Expected impact on services: Routed traffic to this subnet will be disrupted for up to 5 minutes. StorNext service (MDSS) is the only expected customer-visible impact.

Nature of work: Immediately following the above work, any devices remaining on the legacy network in row BA of the data hall at the Information Technology Facility (ITF) will be physically migrated to the new datacenter network fabric.

Expected Impact on services: Impacted devices (and related services) have and will be notified in separate and focused communications with system and services owners.

Service(s) affected
Category
Planned Maintenance
Last updated