Saturday, April 21, 2018 - 6:00am
Saturday, April 21, 2018 - 8:00am

Scheduled work:  OS Firmware update on the Dell EMC Unity 550F all-flash SAN storage array

Data center(s):  Information Technology Facility (ITF)

Expected Duration:  1-hour (6 AM - 7 AM)

Expected impact on services:  Non-disruptive upgrade.  No impact on services


Scheduled work:  Software updates and server reboot if needed for itf-rs-store16 and lc-rs-storage02

Data center(s):  Information Technology Facility (ITF) and Lindquist Center (LC)

Expected Duration: 1-hour max (7 AM - 8 AM)

Expected impact on services:  Minimal unless the updates demand a reboot.  Compliant LSS Pilot service might be unavailable and users should plan accordingly.  This affects the pilot systems only, Large Scale Storage (LSS) and HPC attached storage will not be affected.

Last updated: 
Friday, March 23, 2018 - 1:31pm