Scheduled work: Upgrade the F5 chassis system software to stay current with releases, improve reliability, address security issues, and provide new features
Data center(s): Information Technology Facility (ITF) and Lindquist Center (LC)
Expected Duration: 4-hours (4 AM - 8 AM)
Expected impact on services: Non-disruptive upgrade. No impact on services
Scheduled work: Software updates and server reboot if needed for itf-rs-store16 and lc-rs-storage02
Data center(s): Information Technology Facility (ITF) and Lindquist Center (LC)
Expected Duration: 1-hour max (7 AM - 8 AM)
Expected impact on services: Minimal unless the updates demand a reboot. Compliant LSS Pilot service might be unavailable and users should plan accordingly. This affects the pilot systems only, Large Scale Storage (LSS) and HPC attached storage will not be affected.