ITS will be applying the quarterly Oracle security patch to all production Oracle servers. The security patch install requires that all instances on the server be brought down, the install will take approximately 10 minutes per host. Below is an approximate schedule for each host.
 
Server           Time
fprod-db         3:30am
hprod-db        3:50am
scone             4:10am
garlic              4:20am
bagel              4:30am
popo               4:40am
hoagie            4:50am
toast               5:10am
crepe              5:20am