Start:
Saturday, April 18, 2020 - 5:00am
End:
Saturday, April 18, 2020 - 8:00am
Description
Scheduled Work: The ITS Network Services team is rolling out a priority software code upgrade to the data center routers and production switches
Data Center(s): Lindquist Center (LC)
Expected Impact on Services: The upgrade has been tested successfully in the lab via in-service software upgrade (ISSU), which is non-disruptive. There is one switch upgrade that will cause a disruption. For that specific upgrade case, communication to affected hosting partners is being handled through a separate channel.
Expected Duration: 3 hours