Start: 
Sunday, November 15, 2020 - 4:00am
End: 
Sunday, November 15, 2020 - 8:00am
Description

Nature of the work – Upgrade the F5 GTM and LC LTM system software to stay current with releases, improve reliability, address security issues, and provide new features.
Which data center(s) – LC & ITF
Expected impact on services – None

The F5 GTM/DNS systems provide the same DNS information. The ITF F5 GTM/DNS system will be upgraded first followed by the LC F5 GTM/DNS system. The LC F5 LTM systems are a redundant pair in each data center. The F5 LTMs in LC will be upgraded as follows:

  1. Upgrade standby LTM
  2. Shift services from the primary LTM to the standby LTM
  3. Allow service and application owners ONE HOUR (*) to test their applications against the new LTM software
  4. Upgrade primary LTM
  5. Shift services from the standby LTM back to the primary LTM

(*) In between the upgrade of the standby and primary LTMs, services will be shifted to the upgraded LTM. At that time, system and application owners will be given a ONE HOUR time block to test their applications and services against the new LTM software. If no major issues are discovered, the second LTM will be upgraded and the process will be complete. Estimated start time for this one hour block is around 05:30am, but encourage customers to be on the conference bridge ahead of time to take full advantage of the one hour block.

Last updated: 
Sunday, November 15, 2020 - 8:00am