First Upgrade
Nature of the work: Router software upgrade. The network router software upgrade is designed to be "in-service" with no impact to operations. Infrastructure Day is being utilized to be on the safe side.
Which data center: Information Technology Facility (ITF)
Expected impact on services: none; should be an in-service upgrade
Expected duration: 4 hours
Date and Time: Sunday September 11, 2016 from Midnight - 4AM
Second and Third Upgrades
Nature of the work: Upgrade the F5 LTM systems (one redundant pair in LC and one redundant pair in ITF).
The LC standby LTM will be upgraded first after which, the LC standby LTM will then take over load-balance functionality while the LC primary LTM is upgraded. Once the LC primary LTM is upgraded, load-balance functionality will move back from the standby to the primary. No LC service impact is expected.
The same process will be repeated with the F5 LTM pair in the ITF Data Center
Which data center: Lindquist Center (LC) and Information Technology Facility (ITF)
Expected impact on services: none
Expected duration: 4 hours; 2 hours in LC (4AM - 6AM); 2 hours in ITF (6AM-8AM)
Date and Time: Sunday September 11, 2016 from 4AM - 8AM